Temporary GEPCO Connection

Apply for Temporary GEPCO Connection for Events & Construction – 2025 Guide

If you need electricity for a short time (to get it started or to get off), GEPCO offers temporary connections. These are helpful for events, functions (weddings or parties), or construction work (building a house or shop). There are two types of temporary GEPCO connections:

    i.          Residential Temporary Connection: For residential use

   ii.          Industrial or Construction Temporary Connection: Industrial or Construction use.

The step-by-step process for both is explained below (in easy words, for every one) on this page.

A temporary GEPCO electricity connection is valid for up to six months (good for multiple weddings or construction of a house). To use it for more than six (06) months or 180 days, you must submit a written application to GEPCO.

Along with the application, you will also need to pay the new demand notice to extend the temporary connection (nothing is free in 2025). This applies to both residential and construction use under GEPCO WAPDA distribution.

Check your latest Gepco  bill here.

How to Apply for a Residential Temporary Gepco Connection in 2025

If you construction your house (a dream of everyone) and you need a temporary GEPCO electricity connection for new house construction, follow the steps given below. If you are looking for a new permanent GEPCO connection (after construction of the house is complete), click here for full details.

GEPCO Temporary Connection in 2025, Online Application Form (Step-by-Step Guide)

You can now apply for a temporary GEPCO electricity connection online (very simple and easy). Just follow these simple steps (like 1, 2, 3):

How to Fill the Online Form (simple):

GEPCO Temporary Connection in 2025 Online Application Form Step by Step Guide

Open the online GEPCO application form – Apply Here

Click the “Apply” button on the left side of your screen

Select your company name: Choose GEPCO

Select your subdivision (e.g., MALIKWAL)

Choose your load category (e.g., 15KW)

Enter your neighbor’s reference number (Good if it is in your street)

Select connection type: Choose Temporary

Fill in your personal details

Mention how many meters are already registered under your name

Required Documents for GEPCO Temporary Meter Application:

To complete your GEPCO online application, upload these documents:

Copy of property papers (image file)

Attested CNIC of applicant (image file)

Attested CNIC of witness (image file)

Copy of neighbor’s GEPCO electricity bill

Wiring contractor’s test report

What to Do After Submitting the Online Form:

Print all submitted documents

Put them in a file and submit to your GEPCO subdivision office

GEPCO will check your application and visit your site

After approval, they will issue a demand notice

Print the demand notice, attach the test report, and pay the required fee at the bank

Want to track your GEPCO application? Visit this tracking page.

Temporary GEPCO Electricity Connection for Industrial Use in 2025:

Need a temporary GEPCO connection for industrial work? Follow the same process above and choose the industrial category while applying online.

Industrial Temporary GEPCO Connection in 2025 – How to Apply (simple and easy)

Industrial temporary connections are given by the Punjab Industrial Energy Department, not directly by GEPCO (to make it countable…).

Steps to Apply (First Thing First):

Download the application form – Click Here

Fill the form completely and sign it

Add a cover letter (professional way) with your application

Attach the required documents, CNIC, Allotment & Possession Letters (see below)

Submit the full file to the Punjab Industrial Energy Department office

Required Documents:

Copy of CNIC of the owner and witness

Copy of Allotment Letter

Copy of Possession Letter

After you submit your application (for temporary connection) to the concerned office, the Electrical Department – PIEDMC will review it. If it is complete in all respects without any issue, you will get it. They will then issue a demand notice.

You must pay the demand notice (money is the key) to move forward (no excuse in it). Once the payment is made, the industrial electricity connection will be provided (hopefully, as soon as possible, ASAP).

For more help, you can call the GEPCO helpline.

To check your new GEPCO bill online, click here.